Website Redesign Project Plan Template: Six Phases in a Sheet, With Owners and Gates

A website redesign project plan you can copy into a spreadsheet: six phases, 24 tasks, one accountable name per task, and a gate at the end of each phase.

Summarize with AI
Octo Agency cover: Website Redesign Project Plan Template, with a purple hexagon pattern

Google's site-move documentation says redirects from old URLs should stay in place for generally at least a year, and that a medium-sized site can see rankings move for a few weeks or more after launch. Most redesign plans end on launch day. The plan below does not, because the phase after launch is where the traffic is kept or lost.

This page is a project plan you can copy into a spreadsheet: six phases, 24 tasks, one accountable owner per task and a gate that closes each phase. The thresholds in the gates come from Google, the W3C and WebAIM; the phase structure is ours, and we say where.

Why a redesign plan needs gates, not just dates

A redesign is a common project and an easy one to let drift. Databox found about 49% of small and mid-sized companies had fully redesigned within the past two years, and Orbit Media's tracking of 50 top marketing sites put their average lifespan at two years and one month. Most marketing teams will run one of these every few years, which is not often enough to have a process anyone remembers.

Dates alone do not stop a redesign slipping. A plan with dates and no gates lets design start before the page map is agreed, and lets launch happen before the redirects are tested. Each phase below ends with a gate: a yes-or-no question, the evidence that answers it, and the one person who says yes. Work on the next phase can start early. Sign-off on it cannot.

The model borrows from the UK Government Digital Service, which runs services through discovery, alpha, beta and live, with an explicit decision at the end of each. GOV.UK's service manual puts a typical discovery at 4 to 8 weeks and an alpha at 6 to 8. Those durations are for new public services, not marketing sites, and they are a useful warning: if your redesign's discovery is heading towards GOV.UK territory, it has become a different project.

The six phases at a glance

The six phases, their owners and their gates
PhaseWhat it producesAccountableGate questionEvidence that passes the gate
1. Discovery and baselineGoals, current numbers, constraintsMarketing leadDo we know, in numbers, what the new site must do better?Baseline sheet: traffic, leads, top pages, Core Web Vitals
2. Content and structureContent inventory, page map, URL mapMarketing leadDoes every old URL have a destination and every new page a reason?Inventory marked keep, update or remove; signed page map; redirect sheet
3. DesignKey page designs and componentsDesign approverDoes this look like us, and does it work at phone width?Approved home, main service and contact designs
4. Build and contentStaging site, CMS, forms, trackingAgency leadIs everything on staging that will be on the live site?Staging link with real copy; every form tested end to end
5. QA and launch readinessQA record, redirect testAgency leadDoes the site pass every launch threshold?QA record; redirect test log; accessibility and speed results
6. Launch and watchLive site, 30-day reportMarketing leadWhat changes first, based on real traffic?Before-and-after comparison against the phase one baseline

Source: Octo Agency process; gate thresholds from Google Search Central, web.dev and W3C

The sheet: 24 tasks with owners

Copy this table into a spreadsheet and add five columns to the right: Consulted, Informed, Start, Due and Status (Not started, In progress, Blocked, Done). Add an Evidence column with a link to the file that proves each gate task is done. The role names are generic; replace them with people. Responsible is the person doing the work; Accountable is the one person who signs it off. A task may have several people responsible but only one accountable, which is the rule Atlassian's RACI guide sets out.

Website redesign project plan, task sheet
IDTaskResponsibleAccountableGate task
1.01Write three to five measurable goals for the new siteMarketing leadSponsorYes
1.02Set GA4 retention to 14 months and export 12 months of traffic and conversionsAnalytics ownerMarketing leadYes
1.03Export Search Console queries and pages for the past yearSEO leadMarketing leadYes
1.04Interview sales on won and lost dealsStrategistMarketing leadNo
1.05List constraints: brand, legal, integrations, CMS, budgetAgency leadSponsorNo
2.01Crawl the current site and build the content inventorySEO leadMarketing leadNo
2.02Mark every page keep, update or removeContent leadMarketing leadYes
2.03Write the page map with one headline per pageStrategistMarketing leadYes
2.04Map every old URL with traffic or links to a new URLSEO leadMarketing leadYes
2.05Define CMS collections and fieldsDeveloperAgency leadNo
3.01Design the homepage, main service page and contact flowDesignerDesign approverYes
3.02Extend the components to the remaining templatesDesignerDesign approverNo
3.03Check designs at phone, tablet and wide desktop widthsDesignerAgency leadNo
4.01Build templates and CMS on stagingDeveloperAgency leadNo
4.02Enter or migrate final copy and imagesContent leadMarketing leadYes
4.03Wire forms to the CRM and test each one end to endDeveloperAgency leadYes
4.04Install analytics and define conversion eventsAnalytics ownerMarketing leadYes
5.01Run QA across browsers and widths and keep a recordQA leadAgency leadYes
5.02Run an accessibility scan and fix the failuresDeveloperAgency leadYes
5.03Import the redirects and test a sample of old URLsSEO leadAgency leadYes
5.04Remove staging noindex and check robots.txtDeveloperAgency leadYes
6.01Launch early in the week and submit the new sitemapDeveloperMarketing leadNo
6.02Watch Search Console, analytics and forms daily for the first weekSEO leadMarketing leadNo
6.03Compare 30 days against the baseline and choose the first changeStrategistMarketing leadYes

Source: Octo Agency template

Three rows are where most plans differ from this one. Task 1.02 exists because GA4's retention setting only covers explorations and funnel reports, and a property left on two months cannot give you the year-on-year funnel comparison you will want in phase six. Task 2.04 sits in phase two, before design, so that the page map is tested against the URLs you already rank for. Task 6.03 is the only gate after launch, and it is the one that tells you whether the redesign worked.

Phase two is where a redesign keeps its traffic

The Databox figure that 40.15% of companies delay a redesign over SEO concerns is a fair fear with a procedural answer. Google's site-move guidance lists what to do, and nearly all of it belongs in phase two rather than the week before launch.

Build the old URL list from four places. Google suggests sitemaps, Search Console's links report, server logs and analytics, and says to prioritise the pages with the most traffic and links. Images, PDFs and other files with links pointing at them move too.

Use the inventory to decide, not just to list. Nielsen Norman Group defines an inventory as the list of what exists and an audit as the judgement on it: each item rated high, mediocre or low, then marked keep, update or remove, with an owner for every update. That status column drives the redirect sheet. Kept pages map one to one. Removed pages either redirect to the closest equivalent or return a 404 or 410.

Do not send everything to the homepage. Google warns that redirecting many old URLs to one unrelated page can be treated as a soft 404. Merged content can redirect to the merged page.

Keep chains short. Google asks for redirects straight to the final URL, and where that is not possible, chains of ideally no more than three hops and fewer than five. A site on its second or third redesign usually has chains already; phase two is where they get flattened.

Know your platform's import rules. On Webflow, a CSV import of 301 redirects overwrites every existing redirect on the site, the file can be up to 16MB, and the redirects only take effect after the site is published. Export the current list first, merge it, then import. We build marketing sites in Webflow, so this is the platform we know best; other platforms have their own versions of the same trap.

The page map itself is covered in B2B Website Strategy: How to Write the Page Map Before Anyone Opens Figma. This plan only needs it signed before phase three starts.

The launch gate: thresholds you can check

Phase five is the gate that most needs numbers, because "it looks fine" is not a test. These are the checks we would put in the QA record, each with a pass mark from the body that sets it.

Phase five launch thresholds
CheckPass markSet by
Largest Contentful Paint2.5 seconds or less at the 75th percentileweb.dev, Core Web Vitals
Interaction to Next Paint200 milliseconds or lessweb.dev, Core Web Vitals
Cumulative Layout Shift0.1 or lessweb.dev, Core Web Vitals
Text contrastAt least 4.5:1, or 3:1 for large textW3C, WCAG 2.2 criterion 1.4.3
Images, form fields, links, buttonsAlt text, labels and accessible names on every oneW3C, WCAG 2.2
Page languageSet on every templateW3C, WCAG 2.2
Redirect typePermanent, 301 or 308Google Search Central
Redirect chainsIdeally three hops or fewerGoogle Search Central
Removed pagesReturn 404 or 410, not a homepage redirectGoogle Search Central
IndexingNo leftover noindex or robots.txt block from stagingGoogle Search Central

Source: web.dev Web Vitals, 2024; W3C WCAG 2.2, 2024; Google Search Central, 2026

The Core Web Vitals thresholds are field measures, so a staging site can only be tested in the lab. Treat lab results as a warning light before launch and confirm the field numbers in phase six.

The accessibility rows are there because the failures are common and cheap to fix before launch. WebAIM's 2026 scan of the top million home pages found low-contrast text on 83.9% of them, missing image alt text on 53.1%, missing form labels on 51%, empty links on 46.3%, empty buttons on 30.6% and no document language on 13.5%. A redesign that ships any of those has added a known defect to a brand-new site.

On permanent versus temporary redirects, Google's documentation is clear that 301 and 308 redirects pass the canonical signal to the target, while 302 and 307 leave the old URL eligible to stay in results. A redesign is permanent, so its redirects should be too.

How long each phase takes

Durations depend on page count, content and how fast decisions come back. Our marketing-site process runs all six phases in four weeks, and our published account of it says the usual four-month slip is about two weeks of building and fourteen weeks of waiting for decisions.

The six phases in a four-week schedule
WeekPhasesDecision at the end of the week
Week 11. Discovery and baseline; 2. Content and structureIs this what we sell?
Week 23. DesignDoes this look like us?
Week 34. Build and content; 5. QA and launch readinessIs anything missing before the domain is pointed at the site?
Week 46. Launch and watchWhat changes first, based on real traffic?

Source: Octo Agency, Why a marketing site takes four weeks, not four months, 2026

The schedule holds on two conditions: copy exists or is written alongside the page map, and each review is a 30-minute call with the two approvers rather than days of comment threads. On the USLege redesign, the first version shipped in under a month and replaced a four-page site; the site later grew past 500 pages, which is the argument for settling CMS fields in phase two rather than adding them later. Our white-label builds for Web Tonic run two to three weeks per site.

When we would plan longer: a migration of several hundred URLs, content that has to be written from scratch, or a sign-off chain longer than two people. In each case we would lengthen phases two and four, not the gates. We quote each redesign per project once the page count and the content plan are known.

Running phase six without guessing

Phase six starts on launch day and ends with task 6.03, the 30-day comparison. Google's site-move guidance names the reports to watch: the sitemap report for the new URLs being picked up, page indexing for errors and the old URLs dropping out, and the performance report for new URLs gaining impressions. It also says to expect temporary ranking fluctuation, and that a medium site often takes a few weeks or more to settle.

That is why the comparison is at 30 days and not three. Our own process launches early in the week so the first three working days catch broken forms and tracking; the ranking comparison waits for the 30-day mark. The handover documents for the client team are a separate deliverable, covered in The Webflow Client Handover Kit, and the tracking set-up behind tasks 1.02 and 4.04 is laid out in The Analytics Stack for a Four-Week Site Build.

How to use this plan

Copy the task sheet, put a real name in every Accountable cell before the project starts, and refuse to start phase three until tasks 2.03 and 2.04 are signed. If a phase cannot name its accountable person, that is the first risk on the project. Use the launch thresholds as the definition of done for phase five, and book the 30-day review in the calendar on the day you launch. For the cost and frequency data behind a redesign decision, Website Redesign Statistics 2026 has the survey numbers. Our website redesign service page explains how we run these six phases and scope each project.

Frequently asked questions

What should a website redesign project plan include?

It should include the phases, the tasks in each, one accountable owner per task, dates and a gate that closes each phase. The template here uses six phases: discovery and baseline, content and structure, design, build and content, QA and launch readiness, and launch and watch. It has 24 tasks. Include the URL map and redirect testing as named tasks, because SEO concerns stop 40.15% of companies from redesigning at all, according to Databox's 2024 survey.

How long does a website redesign take?

It depends on page count, content and how quickly decisions are made. Our marketing-site process runs the six phases in four weeks, with one decision at the end of each week. Larger migrations take longer, mostly in content and structure. For contrast, GOV.UK's service manual puts discovery alone at 4 to 8 weeks for a new public service, which is a different kind of project from a marketing site redesign.

Who should own a website redesign?

One person on the client side, usually the marketing lead, should be accountable for the project and for most gates, with a single design approver alongside. Atlassian's RACI guidance says accountability is best held by one person and should not be delegated. Several people can be responsible for doing a task. Consulted and informed roles, such as sales and the leadership team, give input or receive updates without holding sign-off.

How do I keep SEO rankings during a website redesign?

Map every old URL with traffic or links to its closest new page, use permanent 301 or 308 redirects, and keep them generally at least a year, as Google Search Central advises. Do not redirect removed pages to the homepage; return a 404 or 410 instead. Remove staging noindex tags, submit the new sitemap, then watch Search Console. Google says a medium site can take a few weeks or more to settle.

What should be checked before a redesigned website goes live?

Check Core Web Vitals against the web.dev thresholds: LCP of 2.5 seconds or less, INP of 200 milliseconds or less and CLS of 0.1 or less. Check text contrast of at least 4.5:1 under WCAG 2.2, alt text, form labels and page language. Test every form end to end, import and spot-test redirects, and remove staging noindex. WebAIM found detectable WCAG failures on 95.9% of top home pages in 2026.

Sources

  1. How to move a site Google Search Central, 2026
  2. Redirects and Google Search Google Search Central, 2026
  3. Web Vitals web.dev, Google, 2024
  4. Web Content Accessibility Guidelines (WCAG) 2.2 W3C, 2024
  5. The WebAIM Million: the 2026 report on the accessibility of the top 1,000,000 home pages WebAIM, 2026
  6. Content inventory and auditing 101 Nielsen Norman Group, 2020
  7. RACI chart: what is it and how to use Atlassian, 2026
  8. How the discovery phase works GOV.UK Service Manual, 2021
  9. How the alpha phase works GOV.UK Service Manual, 2019
  10. Data retention Google Analytics Help, 2026
  11. Import/export 301 redirects Webflow Help Center, 2026
  12. Website age: how often do companies redesign, and what does it cost? Databox, 2024
  13. What is the average website lifespan? Orbit Media, 2026
  14. Why a marketing site takes four weeks, not four months Octo Agency, 2026
  15. USLege x Hearst case study Octo Agency, 2026

Tags

  • Website redesign
  • Project planning
  • Templates
  • Process
Veljko Nikolic

Veljko Nikolic

Co-founder, Octo Agency

Veljko runs the build side of Octo Agency. He has shipped marketing sites for B2B teams in legal tech, health and manufacturing, and writes about what survives contact with a real review cycle.

Mihajlo Stojanovic

Reviewed by

Mihajlo Stojanovic

Co-founder, Octo Agency

Mihajlo runs the technical side of Octo Agency: Webflow builds, custom backends and the systems that keep a site editable after launch. He has shipped more than twenty Webflow sites a year as a white-label partner and writes about what survives contact with a real marketing team.